Thursday, 31 March 2011
"The heat is on, the time is right, It's time for you, for you to play your game. 'Cause people are coming, everyone's trying.."
Monday, 28 March 2011
And they're out of the blocks...
We had a cracking day on Saturday – it all went to plan pretty much which is nice!
I left work early on Friday to get some prep work done ready for ripping apart the spare bedroom on the Saturday. Prep work involved clearing the last of the bits and bobs from the bedroom, moving scaffolding, checking tools and buying some supplies.
Screwfix came up with the goods – well almost. They were out of stock on a few items, but had gloves, and dust mask, and damp membrane (to seal the door) gaffa tape etc. Also, following a long phone call to Screwfix head office I managed to get a new SDS drill J
The drill I bought in April 2009 is just in warranty and has started to play up a little, so on the off chance I rang up to see if I could get a replacement. Unfortunately, the replacement model number is a lesser specification than the one I have – they’ve down graded it basically, so had to pay an extra £30 to get a variable speed drill. Still, considering the absolute hammering the drill has had, I’m pretty happy to pay £30 to get a brand new one!
Now, they didn’t have one in stock in Huddersfield so we had to go to Bradford to pick it up. Not too bad. – once we found it! And as a bonus, Screwfix aren’t picking up the old drill until Tuesday, so I had 2 drills over the weekend. This was good as my good chum Luke volunteered to put a few hours of graft in on Saturday morning. So we both were able to go at it. Brill.
Friday night we also picked up a trailer we were able to borrow to take rubble to the tip, and popped in to the Gleich household to borrow their angle grinder to clean the beam.
We were all set to go.
Saturday Hannah and I both woke up with headaches, but a bit of breakfast and a coffee and w were ready to go. We sealed up the bedroom door using lots of gaffa and taping some damp proof membrane to both sides of the door. This has worked a treat, no dust has gone in to the house at all!
Unfortunately Luke had to leave at half 12 but by that time we had finished getting the plaster off the walls. Cracking.
It then took a couple of hours to get all the rubble bagged up and out the window. A bit of team effort was required there, with me on one side and Hannah on the other dragging the bags out the window.
Next up I took the ceiling down. I wanted to do this to check the roof timbers were all ok, and electrical cables will need to be run through the roof space anyway. It took about an hour or so to get the ceilings down, then a while to get it cleaned up again and shifted out the window. How many rubble sacks do you need to fit a bedroom in? about 32.
Hannah had to go out in the evening to help at an event at church, but during the day she had been cleaning the beams in the kitchen of lime wash and plaster splatters left from when we did the kitchen 18 months ago. It’s a job well done, and something we had put off for a while!
After the ceiling it was time to get down to business with the beam. The beam had brown varnish/paint on it and we wanted to take it back to a more natural colour.
As we did in the living room, I used an angle grinder with a flat disc. It’s quite aggressive but does a grand job. It took over 2 hours and was incredibly dusty and quite awkward due to the pitched roof and lack of head height, but it did the job. It will need some more work to finish it off, but the bulk of it is done now.
So walls stripped, ceiling down and beam stripped. That was a productive Saturday and all the dusty work done! I finished at about 9:30pm, so put in a good 13 hour day – and feel very knackered for it too! A few aches and pains that is for sure. And then we had an hour of sleep stolen from us!
The room is fairly unremarkable really! We wondered what we might find under the plaster, but other than a rotten lintel, which needs some TLC everything is plain sailing – which is good, if a little boring. No interesting stones or features really.
Sunday afternoon we did 2 trip runs to drop off all the rubble and then dropped the trailer back where it belongs.
The evening was spent resting playing Carcassonne, then I had a nap, and Hannah cooked tea (great deal!) before vegging in front of a DVD. Just what the body ordered!
So what’s next? The room is still sealed up as it’s still filthy as! Tonight I hope to clean it and enable us to unseal the door, making access a little easier!
After that I need to get our electrician around to advise on electrics (I think he’ll do all the work to keep it legal – costs a little more but at least it’s a good, safe job then), hopefully I can put the wall boxes on in preparation though!
We need to get someone to look at the lintel as it’s quite rotten!
Next Saturday we take delivery of the mixer which enables us to do the stipple coat in the bedroom next Monday afternoon. Then we’re well away. Looking at 2 to 3 weeks after that for completion. Fantastic!
Still have a few decisions to make regarding flooring and radiator but all in good time!
It’s certainly a good start to project!
Until next time…
Friday, 25 March 2011
Any claimers??
Thursday, 24 March 2011
Conservation Email and Thoughts
I am well thank you, and I am pleased that you now feel ready (after the last episode) to take on further works - very resilient!
Here are the comments in relation to the issues you raise:
1. Floorboards: As the floorboards are modern replacements you will not require listed building consent to paint them, unless it is to a colour that is substantially out of keeping. We can not ask you to replace them with new floorboards.
2. Replacing the gypsum plaster with a lime plaster is an alteration but not one that impacts on the special interest of the building and is, as you know, an enhancement. Thus, no listed building consent would be required and this is fully supported by this team.
3. Secondary glazing would only require listed building consent if it is interfering with any special features, such as original/moulded timber linings. From memory this is not the case at your house, so no listed building consent would be required.
4. Wood Burning Stove - a ridge vent would be acceptable and is much preferred to a standard vent which often sits very proud of the roofscape. You will require listed building consent for this element so we can fully consider the potential impact on the fabric (visual and physical) that feeding and venting the stove would have on the building. It is not too contentious if the vents are inconspicuous and the flue does not protrude through or too close to any significant features.
Kind Regards
Wednesday, 23 March 2011
"Ain't about the ka-ching ka ching, Aint about the ba-bling ba-bling, we just wanna make the spare room change, forget about the price tag"
March already? What happened there? We are ¼ through the year already, which is unbelievable really, but I am loving the light mornings for my ride to work, and the significantly lighter evenings – which means only thing, it’s time to crack on with some DIY.
It’s just over 2 months since my last post – sorry about that. We have done some bits and bobs – but mostly doing planning work for the spare room. But lets start back on January 22nd, the day after my last post.
I left work early that day and went for lunch with Hannah, but when we arrived home we discovered our house was for sale!
Sure enough a man in a van came and took it away. It then re appeared 2 days later just down the road at 5 Mount Road.
So that was a laugh!
The following day (I think) I grouted the tiles in the vestibule – another step forward to completion. Over the next week or so we pretty much finished the vestibule, put some coat hooks up and shifted some gear in for storage – shoe rack etc. We thought it would free up some useful space in the pantry – which it sort of has, but we’ve only used it for storing junk from the spare room while we do that room!
In recent weeks however, our attention has turned to the spare room.
The first task was to clear out the junk! That involved selling the sideboard on ebay. We got a good price for it, but that was the same week as the boiler broke. So Bouk, a big Danish dude picked up the sideboard and left the cash, then the plumber came, fixed the boiler and took the cash. Easy come, easy go. We have hot water now though. (On a side note - I had a hunch it was a diaphragm on the domestic flow circuit but didn’t want to mess about in the boiler. I was right though, and it wasn’t hard to fix. Good to know for the future.)
We spent the afternoon researching at B&Q. Man, stuff its expensive. We have nearly decided on the lights – as always these are tricky due to the low ceiling and beam, but I think we’re going with 2 circuits, one each side of the beam consisting of dimmable white spots. We think this will work well. In one corner of the room we’re going to but lots of shelving, and I think a pendant light is going to go there to make a kind of reading corner. Should be nice and cosy one hopes!
The other item we were pricing up was floorboards. In the morning we lifted a section of the carpet which then had hardboard nailed under it to even out the floor. It took some getting up but once pulled back it revealed the floorboards. We like the idea of having painted floorboards in the spare room. It will give it a nice cottage feel and look and will be quite minimal. We will paint them off white too which will maximise the light and illusion of space we hope! Unfortunately, yet predictably, the floorboards we pulled back were not in good condition.
So the back up plan is to lay new floorboards over the top – kind of like really thick laminate. We compared the price of doing this to laminate, and to laying new carpet, and surprisingly, the floorboard option worked out the cheapest. Remember these things are all relative though! Nothing is actually cheap.
So what’s next?
Well, this Saturday I’m going to strip the plaster off the walls in the spare room. This is a grim task but has to be done. The biggest concern is keeping the dust in the room and not leaking out in to the rest of the finished house! As part of this the door will be taped up so my access will be through the window, which means the pointy topped light above the back door is going to have to be moved!! The window is teeny tiny, so this could be a laugh on Saturday!
The process is going to be get the room sealed up as best as possible, leaving the carpet down and putting a tarp down to put as many layers as possible between the muck and the kitchen and getting the plaster off the walls as quick as possible. It is all mud and horse hair plaster with an thin skim which can be harder to get off than big chunks of gypsum! It will then be bagged up and taken out through the window and taken to the tip. The room will be cleaned as much as possible before unsealing the door.
I’m not sure how long this will take, but I’m aware stripping the varnish/wood stain off the beam is a very dirty job too, so maybe if I have time while everything is sealed I’ll get to have a bash at that too.
Next week I’ll be running cables for the lights and ring main and putting the back boxes on the wall etc.
Next Saturday Pops Ward is dropping off the trailer and mixer so then we will start getting some plaster on the walls.
All go, but we have moved the schedule forward a bit so it’s taken time pressure off the easter holidays and hopefully given me a little more time for writing up my MSc. I’m still hopeful of a leisurely 5 to 6 week turn around from now though. Should be pretty easy (famous last words) as the kitchen took 4 weeks. Relatively, there isn’t much to do.
Having said that, there are plans to re do the render on the front of the house too in the same period…
Despite the tasks in front of us, the mood in the camp is good – it’s exciting to be doing the last room – 1 year ahead of schedule too!
Cheerio for now. I’ll let you know how Saturday rolls.